Notation and units
Unit mistakes in energy modelling produce plausible-looking, completely wrong results.
This page is the book's single source of truth for symbols and units.
Units
Quantity
Unit
Notes
Power
MW
Instantaneous rate. Dispatch targets, availability, limits
Energy
MWh
Power × time. 10 MW for one 5-minute interval = 0.833 MWh
Price / value
$/MWh
Australian dollars unless stated
Value rate
$/h
$/MWh × MW. Multiply by interval length in hours to get $
Shadow price of a MW limit
$/MWh
($/h) per MW
State of charge
MWh, or % of usable energy capacity
Always say which
Time
NEM market time (AEST, UTC+10, no daylight saving)
Stored timezone-aware where possible
Intervals
Concept
Length
Notes
Dispatch interval
5 min
288 per day
Settlement (trading) interval
5 min since 1 Oct 2021 (5MS)
Earlier data: 30 min
Interval label
AEMO labels intervals by their end time
The library documents which convention each dataset uses
Symbols
Symbol
Meaning
\(P_i\)
Power exported by unit \(i\) [MW]
\(\bar P_i\)
Available capacity of unit \(i\) [MW]
\(L\)
Network / connection limit [MW]
\(a_i\)
Participation coefficient of unit \(i\) in a limit [–]
\(v_i\)
Value to the owner of one MWh from unit \(i\) [$/MWh]
\(\lambda\)
Shadow price (dual value) of a constraint
\(\Delta t\)
Interval length [h] (5 min = 1/12 h)
Availability is not one thing
Keep these separate; they are frequently and wrongly treated as equal:
Term
Meaning
Physical capability
What the plant could produce if nothing else limited it
Technical availability
Capability minus outages and derates
Commercial / market availability
What is offered to the market
Dispatch target
What the dispatch process instructs
Actual generation
What was metered